Gilford served as General Contractor for the fast-track construction of a new 9,746 sf facility that accommodates a Sanctuary and church offices. Work at the 2-acre site encompassed erection of a pre-engineered manufactured metal building with windows and added exterior stone and stucco finishes.
Site work encompassed excavation, installation of site utilities, and paving including site concrete and pervious pavement to reduce precipitation runoff.
The interior fit-out included construction of a Baptismal area; mechanical, electrical, and fire protection systems for the entire building; and architectural finishes (drywall, carpet/tile flooring, painting, and other finishes). This project was completed in 10 months.